Below is an excerpt from the Cross Company whitepaper, “4 Ways to Minimize DCS Migration Downtime.”

“Coordinating your tie-ins will involve contractors, maintenance, and production. Planning the details of the migration will include consideration of the personnel team while managing production and maintenance schedules.

An older titanium dioxide plant chose to replace their cable trays and wiring – in conjunction with their DCS migration. Using several teams to perform prep work in the different plant areas allowed them to capitalize on unplanned outages. They also assigned specialized teams during tie-in for valves, motors, and instrumentation – along with a backup team for general work. This concept worked well on shutdown days by maximizing worker proficiency. “

Cross Group - Process Control Integration

Case Study: APACS DCS Migration to Siemens PCS 7

Josh Dalzell | November 30th, 2018 An industrial utility service company in Kentucky needed to upgrade and migrate its distributed control system (DCS), which came with a few challenges. DTE Calvert City (DTECC) made the decision three years ago to upgrade their obsolete Process Suite HMI to APACS OS. For 15 years, APACS DCS had been

Read More »
Cross Group - Process Control Integration

How To Evaluate a Systems Integrator for Your Distillery

John Loose | October 30th, 2018 Evaluating a Systems Integrator for upcoming projects is an important part of the project process and the decision typically affects more than one project. This will end up being a relationship that lasts over a number of projects and multiple years. Documentation A well-established documentation system is a key to

Read More »
Cross Group - Process Control Integration

8 Factors For Process Automation Project Success

Robbie Peoples, P.E. | September 24th, 2018 Complex integration projects can present a level of ambiguity even for seasoned project managers. Keeping a close watch on budget and schedule are critical for success, but are not enough to ensure the project is a success in the eyes of a customer. Maintaining customer satisfaction can be the most

Read More »
Scroll to Top